Sereno Drive And Tennessee Street Pavement Rehabilitation Project

SUMMARY

Pavement Rehab

Rehabilitate the street and include amenities such as signage, pavement reconstruction, removal and replacement of curb, gutter and sidewalk within the public street rights-of-way. The limits of work was Sereno Drive (From Sonoma (SR29) to Tuolumne) and Tennessee Street (From Adm. Callahan to Oakwood)

Cost: $1.25M Engineer's Estimate
$1.37M Final Construction Contract

Status: Project Complete

TIMELINE

  • July 23, 2009 - Invitation for Bid
  • August 13, 2009 - Bid Opening
  • September 15, 2009 - City Council Awards Contract
  • October 5, 2009 - Construction Begins
  • June 7, 2010 - Construction Complete
  • June 22, 2010 - City Council accepts work as complete