SUMMARY
Rehabilitate the street and include amenities such as signage, pavement reconstruction, removal and replacement of curb, gutter and sidewalk within the public street rights-of-way. The limits of work was Sereno Drive (From Sonoma (SR29) to Tuolumne) and Tennessee Street (From Adm. Callahan to Oakwood)
Cost: |
$1.25M Engineer's Estimate
$1.37M Final Construction Contract |
Status: Project Complete
TIMELINE
- July 23, 2009 - Invitation for Bid
- August 13, 2009 - Bid Opening
- September 15, 2009 - City Council Awards Contract
- October 5, 2009 - Construction Begins
- June 7, 2010 - Construction Complete
- June 22, 2010 - City Council accepts work as complete
PROJECT DOCUMENTS
Go to the following location to access project files.
If you have questions contact Aldrich Bautista, Project Manager (707) 648-5306, [email protected]