Benson Avenue Improvement Project

SUMMARY

Benson Ave

Rehabilitate the street and include improvements such as signage, street lighting, pavement reconstruction, removal and replacement of curb, gutter and sidewalk, and water main, fire hydrant, and sewer main line, survey monuments within the public street rights-of-way.

Cost: $1.32M Engineer's Estimate
$1.02M Construction Contract

Status: Complete

TIMELINE

  • February 25, 2009 - Invitation for Bid
  • March 26, 2009 - Bid Opening
  • April 14, 2009 - City Council Awards Contract
  • May 11, 2009 - Construction Begins
  • May 25, 2010 - Construction Complete

PROJECT DOCUMENTS

Go to the following location to access project files.

If you have questions contact David Espinoza, Project Manager (707) 648-4538, [email protected]