SUMMARY
The Vallejo Station Parking Structure Project is a major component of the Vallejo Waterfront Planned Development Master Plan (WPDMP).The project goal is to construct a 1,300 space parking structure for ferry system riders in two phases. It will consolidate the existing surface parking lots located along Mare Island Way from Capitol Street to Maine Street and make way for the development of those waterfront parcels. The parking structure is designed as a joint use facility to accommodate transit-oriented use and commercial space constructed at the ground floor frontages along Georgia Street and Santa Clara Street.
The construction of the southerly half of Vallejo Station, Phase A is complete with approximately 750 parking spaces. Once the Post Office has been relocated and remaining funding obtained, Phase B can be implemented for the remaining 550 parking spaces.
Cost: |
$22.8M Engineer's Estimate
$21.3M Construction Cost to date |
Status: Major construction complete, PARCS to be installed.
TIMELINE
- January 29, 2010 - Invitation for Bid
- March 18, 2010 - Bid Opening
- March 30, 2010 - Notice of Intent to Award
- April 13, 2010 - City Council Awards Contract
- June 1, 2010 - Construction Begins
- October 11, 2012 - Ribbon Cutting Ceremony
PROJECT DOCUMENTS
Go to the following location to access project files. Visit the project website for more information.
If you have any questions contact Aldrich Bautista, Project Engineer (707) 648-5306, [email protected].