SUMMARY
Serving one of Vallejo's most active commercial zones, Admiral Callaghan Lane between, Redwood Parkway and Tuner Parkway, received new layers of asphalt after concrete curb ramps were upgraded in compliance with requirements of the Americans with Disabilities Act of 1990. Flexibility in the project budget allowed for additional paving to turner Parkway as well as paving between Redwood Parkway and Rotary Way.
Cost: |
$898K Engineer's Estimate
$743K Construction Contract (Columbus Parkway to Ramada Inn)
$404K Contract Change Order (Ramada Inn to Turner Parkway)
$293K Contract Change Order (Redwood Parkway to Rotary Way) |
Status: Complete
SCHEDULE
- April 2, 2013 - Advertise for Bids
- April 18, 2013 - Bid Opening
- May 28, 2013 - Award Construction Contract
- June 25, 2013 - Notice to Proceed
- September 26, 2013 - Work Complete (Turner Parkway to Columbus Parkway)
- May 11, 2014 - Begin Work
- September 18, 2014 - Work Complete (Redwood Parkway to Rotary Way)
PROJECT DOCUMENTS
Go to the following location to access project files.
If you have questions contact Josh Sanchez, Project Manager (707) 648-5229, [email protected].