Sacramento Street Bridge

Sacramento Street Bridge Sacramento Street Bridge

SUMMARY:

The Sacramento Street Bridge over Mare Island Railroad is located between Illinois Street and Farragut Ave on Sacramento Street. The bridge was originally built in 1913 and widened in the 1930's.

The existing bridge is a steel framed structure with concrete slab. The bridge was identified to seismic vulnerabilities as per current standards. The City of Vallejo received a grant application approval for replacement of bridge from Caltrans under the Highway Bridge Program (HBP). Funding sources for the project include 88.5% federal funds from HBP and 11.5% local matching funds.

The new bridge and required roadway approach work will bring the bridge crossing up to current design standards in all aspects including horizontal and vertical clearances for Railroad as well as addressing the seismic deficiencies of the existing bridge. Modifications to the existing roadway approaches required to meet the new bridge configurations will also be built. The City of Vallejo is currently starting in the Construction Phase of the Project.

Budget: $8 M Original Engineer's Construction Estimate; $9 M Updated Cost Estimate

Status: Project Design is Complete and Construction Phase is starting in mid-March 2021

Follow the link for the Sacramento Street Bridge Project Factsheet.

PROJECT SCHEDULE

Spring 2021 - Begin Bridge and Roadway Construction

Winter 2021 - Complete Project Construction

**Elevated Construction Noises** Be advised that demolition work will begin on Wednesday, April 21, 2021 for approximately 1 week. Click here for more information from the Project Manager.

FARRAGUT AVE CLOSURE:
Farragut Ave will be closed to thru traffic to allow for utility work needed before the Bridge can be replaced. Access to residences will be maintained during this work. Detour routes during this closure will be clearly identified by local signage.
START: March 17, 2021
END: April 5, 2021

Farragut Closure

SACRAMENTO STREET CLOSURE
Sacramento Street will be closed to vehicle traffic to allow for demolition of the old bridge and construction of the new bridge and roadway approaches. Pedestrian access over the railway and to residences will be maintained during this work. Detour routes during this closure will be clearly identified by local signage. For impacts to bus routes contact Soltrans.
START: April 12, 2021
END: Fall 2021

Sacramento Street

Working hours for the project are Monday through Friday 7:00AM to 4:00PM.

If you have questions contact:
Tom Walker, Project Manager (408) 307-9765
[email protected]

Sunny Jhutti, Construction Manager (415) 246-246-4920
[email protected]

Follow the project here https://www.myvallejo.com/sacramento-street-bridge

Site Powered by: Civiclive © 2004-2024