SUMMARY
This dredging episode removed approximately 14,000 cubic yards of material from the J Dock area of the Vallejo Marina by the October 15 regulatory deadline. Shallow sediment was removed from beneath the main J Dock float, and deeper access was provided to some berths and the sewer pump-out.
Budget: $505K Engineer's Estimate
$493K Construction Contract
Status: Complete
TIMELINE
- May 11, 2016 - Advertise for Bids
- May 26, 2016 - Bid Opening
- July 12, 2016 - Award Construction Contract
- August 12, 2016 - Notice to Proceed
- October 14, 2016 - Work Complete
PROJECT DOCUMENTS
Go to the following location to access project files.
If you have questions contact Josh Sanchez, (707) 648-5229, [email protected].