Corp Yard & PD Security Fence

Sacramento Street Bridge

SUMMARY:

Approximately 1,500 linear feet of dilapidated chain-link fencing will be removed and approximately 1,800 linear feet of new 8ft. tall security fencing will be installed in this project. Six vehicular rolling gates and four personnel gates will also be installed with integrated access control systems installed by a separate vendor.

Budget: $489,000 Engineer's Estimate
$625,000 Construction Contract

Status: Under Construction

PROJECT SCHEDULE

  • August 2, 2016 - Advertise for Bids
  • August 16, 2016 - Bid Opening
  • September 13, 2016 - Award Construction COntract
  • September 19, 2016 - Notice to Proceed
  • February 2017 - Anticipated Completion Date

PROJECT DOCUMENTS

Go to the following location to access project files.

If you have questions contact Josh Sanchez, Project Manager (707) 648-5229, [email protected].

Site Powered by: Civiclive © 2004-2024