SR2S Hogan School Site Improvements

SUMMARY

Install pedestrian countdown signal heads, lighted crosswalk with LED Pedestrian Warning lights (IRWL) and other traffic calming measures at Georgia St., Oakwood Ave., Rosewood Ave. and Westwood St.

Cost: $724K Engineer's Estimate
$450K Construction Contract

Status: Under Construction

TIMELINE

  • February 7, 2013 - Project Advertisement
  • February 26, 2013 - Bid Opening
  • June 13, 2013 - Construction Starts (public notice)

PROJECT DOCUMENTS

Go to the following location to access project files.

If you have questions contact Srinivas Muktevi, Project Manager (707) 651-7107, [email protected].

Site Powered by: Civiclive © 2004-2024