SUMMARY
Rehabilitate the street and include amenities such as street furniture, signage, decorative paving, street lighting, pavement reconstruction, removal and replacement of curb, gutter and sidewalk, and storm drainage modifications within the public street rights-of-way.
Cost: |
$1.95M Engineer's Estimate
$1,86M Construction Contract |
Status: Under Construction with completion anticipated for June 2013.
TIMELINE
- April 17, 2012 - Invitation for Bid
- May 10, 2012 - Bid Opening
- May 21, 2012 - Notice of Intent to Award
- June 26, 2012 - City Council Awards Contract
- July 23, 2012 - Construction Begins
PROJECT DOCUMENTS
Go to the following location to access project files.
If you have questions contact David Espinoza, Project Manager (707) 648-4538, [email protected]