SUMMARY
Following completion of the concrete rehabilitation phase in 2014, this final project phase rehabilitated a segment of Santa Clara Street between Carolina Street and Tennessee Street, and Florida Street between Mare Island Way and Sonoma Blvd. with a new layer of asphalt.
Budget: $1.29M Engineer's Estimate
$1.05M Construction Contract
Status: Complete
TIMELINE
- September 25, 2015 - Advertise for Bids
- October 15, 2015 - Bid Opening
- November 17, 2015 - Award Construction Contract
- March 14, 2016 - Notice to Proceed
- July 1, 2016 - Work Complete
PROJECT DOCUMENTS
Go to the following location to access project files.
If you have questions contact Gary Cullen, (707) 648-5306, [email protected].