Sereno Dr. Pavement Rehabilitation - Measure 'B'

Sereno Dr. Rehab

SUMMARY

Following completion of the concrete rehabilitation phase in 2014, this final project phase rehabilitated an actively traveled segment of Sereno Drive, over a half-mile in length between Tuolumne Street and Fairgrounds Drive. Over 29,000 square feet of deep excavation and repair was completed to better support the new asphalt pavement.

Budget: $903K Engineer's Estimate
$818K Construction Contract

Status: Complete

TIMELINE

  • February 17, 2015 - Advertise for Bids
  • March 12, 2015 - Bid Opening
  • April 14, 2015 - Award Construction Contract
  • April 15, 2015 - Notice to Proceed
  • May 28, 2015 - Work Complete