The City’s public safety answering point (PSAP), also referred to as our public safety dispatch center, is currently located at 111 Amador Street, the building that also serves as the headquarters for the Vallejo Police Department (VPD). The building was built in the 1960’s to house both officers and staff of the police department. However, today, the building is in poor condition and requires maintenance responses frequently.
On April 11, 2023, the Vallejo City Council authorized the design of a new police facility at the Amador location, and the first phase of design is underway. The architects working on the design are on schedule to submit 90% design drawings in November 2024. However, completion of full design and construction of a new police headquarters will take several years, and there is an immediate desire to relocate the dispatch center temporarily until a new police headquarters is completed. On December 13, 2022, the City Council authorized $1.5 million of American Rescue Plan Act (ARPA) funding for a dispatch center relocation project.
The City of Vallejo currently utilizes several state-of-the-art technologies for the PSAP. This highly specialized and mission critical equipment needs to be moved in a systematic manner to a new dispatch location. Unfortunately, the existing equipment simply cannot be taken down and moved to a new location. The major requirement is that the current dispatch must remain in operation due to its critical nature until a new dispatch center is fully ready for operation, which will result in additional cost and lead time for the relocation.
On October 24, 2023, staff presented a technical comparison of potential sites as relocation options to the City Council (new portable buildings at 111 Amador St., 970 Nimitz at the Fire Administration Building, 400 Mare Island Way, and 2 Florida Street). Key issues in evaluating each site included, but were not limited to, back-up generator, moving the PSAP, emergency building specification requirements, ADA improvements, and site and personnel security. Using new portable buildings at Amador Street, being on the same campus as the existing VPD headquarters, met most of the criteria, was the most cost efficient, and provided the most security.
Council's direction to City staff was to move the dispatch center into two modular units at 111 Amador. Staff immediately engaged Indigo Hammond + Playle Architects to prepare architectural design and civil site plans and CSG Consultants to begin the site survey, environmental assessments, and management of this project.
In January 2024, Indigo Hammond + Playle Architects completed the site drawings for the project and sent informal proposal packages to eight modular companies, requesting responses by April 1, 2024. Of the eight solicited companies, three responded that they were unable to meet either the specifications or timeline for completion, while 2 responded, with similar pricing.
At that time, staff expected that one manufacturer, Whitley, would be able to complete construction of the two modular units, deliver the two units to the Amador site, and have City staff complete the site work in August/September 2024; a contractor would be able to install the units at the site in September 2024; and a City IT vendor would be able to complete the relocation of the PSAP and other communications work and dispatch would be able to go live in January 2025.
In May 2024, staff received Council approval relating to the acquisition and construction of the modular units in the amount of $485,849, which included the cost of the modular units, installation of the units, installation of ADA ramps, landing and awning, as well as furniture installation.
From May 2024 through October 2024, contract execution was delayed due to company name, construction qualifications, bonding and insurance requirements. One major issue was that the contract was drafted and approved for Whitley Manufacturing Co. while the modulars were being manufactured by the sister company, Whitley Evergreen. In addition, during the contracting process it came to light that neither Whitley Manufacturing nor Whitley Evergreen is licensed for installation of the portables being purchased, which also created issues with bonding requirements for the installation construction work. After working with the City Attorney’s office and the contractor, the City will enter into a Purchase Agreement with Whitley Evergreen for the fabrication and delivery of the modular units. Staff is currently in the process of contract execution, and once that is complete, a first payment will be made to Whitley Evergreen. To date, no payments have been made toward the purchase of the modular buildings. Once Public Works receives the schedule of delivery from Whitley Evergreen, Public Works will enter into a construction contract with a State of California C47 licensed contractor, which is a certified contractor that specifically installs manufactured buildings.
Due to the delay in contract execution, the modular build window has shifted delivery of the units to Q1 of 2025. The Public Works Department will perform all trenching, site work, and fence/wall work in preparation for the delivery of the modular buildings. City staff currently anticipates that the two units will be delivered and the site work will be completed in January/February 2025; the contractor will install the unit, ADA ramps, landing and awning, and furniture in February/March 2025; and a City IT vendor will complete the relocation of the PSAP and other communications work and dispatch will be able to go live in June/July 2025.
The dispatch center will occupy the two modular units until the new PD Building is completed.