SUMMARY
In support of Mare Island's increasing activity and development, a top layerof layer of asphalt was removed and replaced at various street segments of Azuar Drive, G Street, Nimitz Avenue, Railroad Avenue, and Walnut Avenue for improved ride quality.
Cost: |
$533K Engineer's Estimate
$450K Construction Contract |
Status: Complete
SCHEDULE
- July 12, 2012 - Advertise for Bids
- August 30, 2012 - Bid Opening
- September 18, 2012 - Award Construction Contract
- October 5, 2012 - Notice to Proceed
- November 2, 2012 - Work Complete